The establishment of the Common Secured Landfill Facility became necessary to facilitate disposal of solid waste being generated by industrial units in an environmentally safe manner. This was also necessary to fulfil the requirement of the provisions of Hazardous Waste (Management and Handling) Rules 198 framed under Environment (Protection) Act 1986. Keeping these requirements in mind the GESCSL had developed and constructed a Common Secured Landfill Facility for the safe disposal of solid waste generated by industrial units.
SLF DETAILSPARTICULARS | SLF – 1 | SLF – 2 | EXPANSION OF SLFs 1 & 2 | SLF – 3 | TOTAL |
---|---|---|---|---|---|
Development Stage | Phase : 1 | Phase : 2 | Phase : 3 | Phase : 4 | - |
Capacity | 75000 MT | 170000 MT | 130000 MT | 850000 MT | 1225000 MT |
Period of Operation | APR.98 – JAN.99 | FEB.99 – OCT.01 | OCT.01 – FEB.03 | MAR.03 – Till date | APR.98 – Till date |
Utilization | 74287 MT | 170004 MT | 128441 MT | 750702 MT | 1123434 MT |
Total Cost | Rs.0.93 Cr. | Rs.1.66 Cr. | Rs.0.81 Cr. | Rs.11.50 Cr. | Rs.14.90 Cr. |